What Hyperscale Data’s $1.2 billion AI hosting estimate includes

0

Hyperscale Data’s quarterly filing puts the potential value of its Michigan data-center hosting agreement at about $1.2 billion if the customer exercises two five-year extensions and the provider meets its contractual obligations.

The estimate spans up to 20 years

The agreement has an initial ten-year term. For each phase, the clock starts when the company delivers the designated space and electrical capacity to the customer. The two five-year options account for the rest of the period covered by the headline estimate.

The filing also estimates about $74.8 million in remaining project payments between November 2026 and March 2027, subject to changes in cost and timing. Project spending is therefore nearer term than much of the potential contract revenue.

Hyperscale Data Form 10-Q